1. Establishment of Plant System
  Approval on establishment of plant Location Assignment Approval Approval of new business plan
Processing Period 30 days 60 days 45 days
Legal Process 15 of laws
(23 of permission)
16 of law
(25 of permission)
14 of law
(25 of permission)
13 of law
(23 of permission)
13 of law
(23 of permission)
6 of law
(10 of permission)
Process Guide Plant Location Total Standard Guide Manufacturing industry location development guide
(Ministry of Construction and Transportation)
Total business process guide for new business plan
(Ministry of Commerce, Industry and Energy)
Change of use Impossible Impossible Possible
Tax Deduction & Fund aid n/a n/a Tax deduction
(Corporation, Income, Acquisition)
Application Approved when individual laws are fulfilled Approved when individual laws & location assignment requirements are fulfilled Approved when individual laws are fulfilled and classified as techno industry.
 
2. Plant Establishment Registration Process
1 Applying Company Apply for plant establishment approval - possible plant locations
- application, business plan, and other required documents
- apply in the permission division
2 Mayor/Governor Agreement on related divisions - reviews in various points
- review appropriateness of location
- review environmental effects
- possibility of construction permission
3 Mayor/Governor Issue plant establishment approval  
4 Applying Company Build plants - construction permission
- report starting construction
- inspection of mid construction
- inspection of building usage
5 Applying Company Report of plant construction completion - set up machinery
- report machinery & equipment within 2 months after set up